Client: Nix Anderson
Project: Gold Coast University Hospital Car Park Stage 2
Duration: July 2016 – September 2016
Project Value: $398,000
Project Details: Following on from Stage 1 works construction of the remainder of the car park commenced in July. Works undertaken were similar to those in stage 1 being earthworks, kerb and channel, stormwater drainage, line marking and car stops, lighting and also retaining wall works. The completion of stage 2 will provide an additional 140 car parking spaces.
We are working hard at South Pine Sports Complex to finalise construction of the new soccer facilities. These facilities which include a High Performance Club House and a Local Club House facility along with 4 new soccer fields will provide a much welcome addition to the complex. We are sure that after the excitement of the World Cup Soccer recently held in Australia that soccer clubs will be receiving an influx of players.
28/09/2023