Client: Nix Anderson
Project: Gold Coast University Hospital Car Park Stage 2
Duration: July 2016 – September 2016
Project Value: $398,000
Project Details: Following on from Stage 1 works construction of the remainder of the car park commenced in July. Works undertaken were similar to those in stage 1 being earthworks, kerb and channel, stormwater drainage, line marking and car stops, lighting and also retaining wall works. The completion of stage 2 will provide an additional 140 car parking spaces.
As 2024 draws to a close we reflect on the year. South Pine Sports Complex Soccer Precinct was completed at the begining of May and we were pleased to hand over a community asset that will be sure to service the community for many years to come. We have also completed some smaller projects during the year and we now look forward towards 2025 with anticipation.
04/12/2024