Client: HCE Engineers Pty Ltd
Project: Byng Road Subdivision, Birkdale
Duration: May 2010 to December 2010
Project Value: $700,000
Project Details: This project started as an overgrown horse paddock which was slashed and cleared to allow work to commence. The subdivision works consisted of stormwater, sewer and water pipe laying and connection to mains. A road extension to create a cul-de-sac was required to provide car access to the lots. Bad weather caused many delays as the ground was unworkable for the machines. After months of hard work, the clients were ecstatic with the finished product.
What a year! 2019 passed us by in a whirlwind - Hello 2020! We are extremely proud of our Main Constructions family for their continued hard work and dedication as we begin a new decade. We are excited to head into this year with a passion to succeed and deliver first class quality projects on time and on budget to our clients. We are in the process of finalising projects at Nathan Road Sports Fields and James Drysdale Baseball Fields and are looking forward to works commencing at Les Hughes Sports Complex along with works continuing at Bill Brown Reserve.
30 January 2020