Client: A Aufferber
Project: Buchanan Road Drainage
Duration: March 2016
Project Value: $200,000
Project Details: Works for this project involved updates to the property to improve drainage. This involved the demolition of an existing spoon drain, concrete and removal of stormwater pipes and associated connections from the building. New works involved earthworks to reshape the existing gravel hardstand to drainage lines and supply and install stormwater and connect to downpipes. Concrete works included the construction of a 407m2 slab, 125mm thick upstand concrete retaining wall and construction of an 80m long concrete spoon drain.
As 2024 draws to a close we reflect on the year. South Pine Sports Complex Soccer Precinct was completed at the begining of May and we were pleased to hand over a community asset that will be sure to service the community for many years to come. We have also completed some smaller projects during the year and we now look forward towards 2025 with anticipation.
04/12/2024