Client: Moreton Bay Regional Council
Project: Ira Buckby Rd Footpath
Duration: Jan – Feb 2016
Project Value: $ 75,900
Project Details: This project involved the installation of a 1.5m wide reinforced concrete pedestrian footpath along Ira Buckby Road. These works were carried out under a traffic management plan as concrete had to be poured from the road with limited access to the work area. Turf was laid to finish off the project and maintenance carried out for four weeks to establish.
We are working hard at South Pine Sports Complex to finalise construction of the new soccer facilities. These facilities which include a High Performance Club House and a Local Club House facility along with 4 new soccer fields will provide a much welcome addition to the complex. We are sure that after the excitement of the World Cup Soccer recently held in Australia that soccer clubs will be receiving an influx of players.